The time to discuss underground utility documentation is before the contractor is ready to cover the installation. For an as-built record—a record of what was installed rather than simply what was designed—make survey coordination part of the work plan. FHWA warns that old site plans and as-built diagrams may be unreliable and that relying too heavily on them can leave unknown utilities undiscovered until construction.
The following checklist is a suggested coordination framework, not a universal survey specification. Use it to agree on what will be captured while utilities are visible, how gaps will be reported, and who will receive the finished records.
Agree on the capture plan before installation
FHWA identifies reliable utility location and depth information, along with accessible storage, as important to efficient project delivery. Start with those goals rather than a vague request to “get the as-builts.”
Ask the contractor, surveyor, and owner or project engineer to settle these questions:
- Scope: Which utility runs, connections, structures, and installation stages should be documented?
- Timing: Who notifies the surveyor that a section is ready, and how will changes to the installation schedule be communicated?
- Review: Who checks whether the agreed capture is complete before the project team proceeds with covering that section?
- Delivery: Who receives the field information and final record, and where will both be stored?
Define a project-specific review point before backfill. Do not assume that this suggested workflow establishes a legal hold point or gives the surveyor authority to approve construction. Confirm responsibilities with the owner and the professionals managing the work.
A practical pre-backfill capture checklist
Use the items below as scope questions for the surveyor, not as a claim that every project requires the same measurements.
Locations and elevations
- Which points along each utility should have measured locations?
- Where should elevations—vertical positions relative to an agreed reference—be recorded?
- What part of the utility does each measurement describe?
- What location and elevation references should accompany the delivered information?
Ask for measurement descriptions that another person can interpret without guessing. Avoid requesting only a “depth” value without also asking what that value is measured from and to.
Fittings, connections, and field changes
- Should the scope include bends, branches, fittings, valves, service connections, and endpoints?
- How should each captured feature be identified in the record?
- Who will communicate changes from the design, including rerouted sections or revised connections?
- How will the team distinguish survey measurements from contractor notes or information taken from plans?
For example, if a connection is moved during installation, ask the team to flag the change for review rather than simply carry the planned connection into the final drawing. This is a proposed documentation practice, not a prescribed measurement standard.
Gaps and handoff
- Has each section in the agreed scope been reviewed for completion?
- Are covered, inaccessible, or otherwise unmeasured portions clearly identified?
- Is someone assigned to resolve questions and deliver the final files?
FHWA identifies missing responsibility, inconsistent formats, lack of centralized storage, and references to changed surface features as utility-record problems. A clear handoff and a retrievable record should therefore be part of the plan, not an afterthought.
Do not let the survey schedule override excavation safety
A documentation deadline is not a reason to enter an unsafe excavation. OSHA requires employers to have a competent person inspect trenches daily and as conditions change, before worker entry. A competent person can identify excavation hazards and has authority to take prompt corrective action.
Coordinate survey access with the employer responsible for excavation safety. These points are not a complete excavation-safety checklist. Requirements vary by state; confirm applicable requirements with the relevant safety authority and qualified project personnel.
Keep as-builts separate from future utility locating
A useful as-built is an input to future investigation, not proof that every underground facility is shown. FHWA treats as-built plans, old project plans, and maintenance records as sources for utility research. It also notes that even surveys of visible facilities correlated with records can reveal omitted or incorrectly plotted utilities.
Utility-locating surveys reduce uncertainty, but FHWA cautions that not all utilities are detectable. For future digging, contact 811 and confirm the applicable process; state requirements vary. Do not substitute the record drawing for that process.
Before the next installation starts, assign the notification contact, agree on the capture questions, and choose the record-storage location. Then use that agreement to review each section before backfill—not to reconstruct missing information at closeout.
Featured image: Image by planet_fox from Pixabay (Pixabay Content License)
Footnotes & Sources
- IV. Site Characterization and Utility Locating – Avoiding Utility Relocations – Publications – Utility Program – Design – Federal Highway Administration, fhwa.dot.gov. — Limits of old plans and as-built diagrams, records used in utility research, and the uncertainty and limitations of utility locating.
- SHRP2 Solutions – 3D Utility Location Data Repository, fhwa.dot.gov. — Importance of reliable utility location and depth data and accessible storage for reuse.
- Applying Subsurface Utility Engineering to Highway and Road Projects – Subsurface Utility Engineering – Utility Program – Design – Federal Highway Administration, fhwa.dot.gov. — Distinction between design and as-built records and utility-record problems involving responsibility, formats, storage, and changed reference features.
- Trenching and Excavation Safety, Occupational Safety and Health Administration. — OSHA trench inspection requirements and the role and authority of a competent person.
- Subsurface Utility Engineering – Subsurface Utility Engineering – Utility Program – Design – Federal Highway Administration, fhwa.dot.gov. — Omissions and incorrect plotting found when visible utility facilities are surveyed and correlated with existing records.
- Trenching and Excavation Toolkit, nahb.org. — Recommendation to call 811 before digging and seek utility-location information before excavation.